Land Basis and Project Readiness
Construction financing starts before the first foundation is poured. Lenders evaluate control of the land, the legal ability to build and the borrower’s ability to execute. A parcel’s purchase price does not prove it is ready for construction. Zoning, access, utilities, drainage, environmental issues and permit status can determine whether a project is financeable at all.
Separate cost basis from appraised land value. If you already own the site, a lender may recognize some eligible equity, but the amount and valuation treatment depend on its rules and any existing debt. Land held for years does not automatically count at a hoped-for development value. Identify liens and the payoff needed at closing.
Assemble plans, specifications, a realistic schedule, permits or a documented permit path, contractor credentials and a detailed budget. Explain whether the project is speculative, presold or intended for rental. These uses have different repayment evidence. A builder’s relevant completed projects can help demonstrate execution capability; experience with small cosmetic renovations may not translate into ground-up development. Order due diligence in a sensible sequence so expensive reports are not commissioned before a fatal entitlement problem is discovered. Clear project readiness reduces uncertainty in both pricing and closing timing.
Worked example
Land cost $100,000 and currently has a $40,000 lien. A lender hypothetically recognizes $100,000 land value, leaving $60,000 unencumbered value before its eligibility adjustments. If recognized value is only $80,000, that falls to $40,000. Neither figure is automatically cash available to pay the contractor.
Mini glossary
- Entitlement
- Approval establishing permitted development rights.
- Land basis
- Recorded investment cost in the site.
- Unencumbered equity
- Value remaining after secured debt, subject to lender recognition.
Put it into practice
Prepare a site-readiness checklist covering title, access, zoning, utilities and permit status. Record land cost, current value evidence and debt separately. Ask the lender what land equity is eligible and which approvals must be complete before closing versus before the first construction draw.
Recommended reading
Use these primary sources for context. Individual lender requirements can change; confirm the current program for your transaction.
