Keep Enough Cash for the Transition
Short-term projects expose the investor to uncertain timing. Contractor delays, permitting, leasing and appraisal review can lengthen the holding period even when the property is sound. Bridge loans therefore require a liquidity plan that extends beyond the closing equity check. Show how monthly payments and property expenses will be covered before stabilized rent or sale proceeds arrive.
Budget carry using conservative assumptions. If an interest reserve is included, determine its size, eligible use and expected exhaustion date. It is borrowed money or allocated funds under the contract, not free profit. For rehab funding, coordinate contractor payments with reimbursement timing and retainage. The available loan commitment may not cover a cash shortage between inspection cycles.
Set early warning triggers. A missed construction milestone should prompt a revised schedule and cash forecast, not simply another optimistic completion date. Contact the lender before an extension becomes urgent, and confirm whether approval is discretionary. Changes in property insurance, taxes or leasing costs can compound delays. Keep liquidity assigned to this project separate from funds already committed elsewhere. The investor should be able to show enough available cash for a credible downside period while maintaining a realistic path to repayment, rather than depending on an extension that has not been granted.
Worked example
Loan interest is $2,000 monthly and property carry is $600. A three-month delay costs $7,800 before extension fees. If liquid cash is $10,000 but $4,000 is committed to the final contractor payment, only $6,000 remains for carry. The downside case already shows a $1,800 gap.
Mini glossary
- Carry
- Recurring ownership and financing expenses.
- Interest reserve
- Earmarked funds for contractual interest payments.
- Liquidity gap
- Scheduled cash needs exceeding available cash sources.
Put it into practice
Build a month-by-month cash forecast through a three-month delay. Deduct funds committed to other projects and known contractor balances. Mark reserve exhaustion and the latest date to request an extension. Identify a concrete cash source for any shortfall instead of listing hoped-for sale proceeds.